When applying for access to the tram corridor the submission times listed below must be adhered to:
Type of work | Submission time | Approval required |
Closure of a line(s) requiring the cancellation of revenue services on a business day | 6 months (26 weeks) | Department for Infrastructure and Transport |
Closure of a line requiring bus substitution | 3 months (13 weeks) | Department for Infrastructure and Transport |
An extended ALBF requiring the cancellation of the first and/or last service(s) | 21 days | Torrens Connect General Manager |
An extended ALBF requiring the cancellation of Fall Ins/Fall Outs | 21 days | Torrens Connect General Manager |
Work requiring revenue services to operate around the worksite either by bidirectional working or using alternative track | 8 weeks | Torrens Connect General Manager |
All other works | 21 days | PTWC |
*Major events will be taken into consideration when reviewing all network access applications |
Note:
- Any application time scale is for the complete application.
- When a document is returned to the applicant for further information, the process period is paused and resets upon receipt of amended application.
- Short notice applications can be considered however the decision is at the discretion of the PTWC.